The project comprises of the construction of a new two storey primary care centre including demolition of the existing NHS Building, external works, landscaping and extensive drainage including large volumes of on site attenuation via 750mm concrete pipework.
Co-ordination was key to the project with large volumes of services within corridors including complex ventilation ductwork due to the quantity of internal rooms along with the building wide need for cooling which was indicated as a requirement via the thermal model carried out.
One of the main challenges was establishing all the differing building end user requirements as the following departments operate within the building:
- Mammography Unit
- Minor Operation Suite
- Community Dental Services
- 4 x GP Practices
- Shared Clinic
- CTP Clinic
- Pharmacy
All materials used were to a high standard to comply with the HTM and ensure minimal long term maintenance.
VALUE: £5.40M
Scheme
Healthcare
Area
Lincolnshire
Location
Grimsby
Client
Lunn Healthcare Facilities
Architect
Health Design Partnership
Structural Engineer
Robinson Consulting
M&E Consultant
Rosedale Building Services
Value
£5m - £10m
Period
60 Weeks